Skip to main content
edited tags
Link
deleted 25 characters in body
Source Link

I am considering the Earling-B or m/m/c/c process.

Let the request arrival rate follows Poisson Distribution, i.e.Process with average rate, $\lambda$ is mean of Poisson Distribution.

Let the service time follows Exponential Distribution, i.e., $\mu$ is the mean of Exponential Distribution.

Let's say, I have a grid of $c \times T$. Here $c=5$, i.e., in the Queueing process, there are 5 servers and 5 requests can be served at most concurrently. Let, $T=100$ is the number of time-slots that I need to simulate. Therefore, each block in the x-axis represents a time-slot and each block in the y-axis is the amount of resource required to serve a request.

For example,

Let the number of requests at the first time-slot is 3. The first and the third requests need service time of 2 times slots, while the second request requires service time of only 1 time-slot.

As a result, in the grid,

The first row will have two grid-element (first and second column) filled

The second row will have one grid-element (first column) filled

The third row will have two grid-element (first and second column) filled

Now, let's say, at the second time-slot, the number of requests is 5. In this case, due to the nature of Earling-B or m/m/c/c Queueing Process, only 3 more requests can be served at this particular time-slot as we already have two requests being served (first and third request arrived at first time-slot). Other requests are blocked or lost.

How do I generate the number of resources being used by the system in different time-slots?

Lets assume, $\lambda=0.2$ per time-slot

$\mu=2$ time-slots

I am considering the Earling-B or m/m/c/c process.

Let the request arrival rate follows Poisson Distribution, i.e., $\lambda$ is mean of Poisson Distribution.

Let the service time follows Exponential Distribution, i.e., $\mu$ is the mean of Exponential Distribution.

Let's say, I have a grid of $c \times T$. Here $c=5$, i.e., in the Queueing process, there are 5 servers and 5 requests can be served at most concurrently. Let, $T=100$ is the number of time-slots that I need to simulate. Therefore, each block in the x-axis represents a time-slot and each block in the y-axis is the amount of resource required to serve a request.

For example,

Let the number of requests at the first time-slot is 3. The first and the third requests need service time of 2 times slots, while the second request requires service time of only 1 time-slot.

As a result, in the grid,

The first row will have two grid-element (first and second column) filled

The second row will have one grid-element (first column) filled

The third row will have two grid-element (first and second column) filled

Now, let's say, at the second time-slot, the number of requests is 5. In this case, due to the nature of Earling-B or m/m/c/c Queueing Process, only 3 more requests can be served at this particular time-slot as we already have two requests being served (first and third request arrived at first time-slot). Other requests are blocked or lost.

How do I generate the number of resources being used by the system in different time-slots?

Lets assume, $\lambda=0.2$ per time-slot

$\mu=2$ time-slots

I am considering the Earling-B or m/m/c/c process.

Let the request arrival rate follows Poisson Process with average rate, $\lambda$

Let the service time follows Exponential Distribution, i.e., $\mu$ is the mean of Exponential Distribution.

Let's say, I have a grid of $c \times T$. Here $c=5$, i.e., in the Queueing process, there are 5 servers and 5 requests can be served at most concurrently. Let, $T=100$ is the number of time-slots that I need to simulate. Therefore, each block in the x-axis represents a time-slot and each block in the y-axis is the amount of resource required to serve a request.

For example,

Let the number of requests at the first time-slot is 3. The first and the third requests need service time of 2 times slots, while the second request requires service time of only 1 time-slot.

As a result, in the grid,

The first row will have two grid-element (first and second column) filled

The second row will have one grid-element (first column) filled

The third row will have two grid-element (first and second column) filled

Now, let's say, at the second time-slot, the number of requests is 5. In this case, due to the nature of Earling-B or m/m/c/c Queueing Process, only 3 more requests can be served at this particular time-slot as we already have two requests being served (first and third request arrived at first time-slot). Other requests are blocked or lost.

How do I generate the number of resources being used by the system in different time-slots?

Lets assume, $\lambda=0.2$ per time-slot

$\mu=2$ time-slots

edited title
Source Link

How to generate number of points in a Queueingm/m/c/c process with Poisson arrival and exponential service time?

I am considering the Earling-B or m/m/c/c Queueing Process asprocess.

QueueingProcess[\[Lambda], \[Mu], c, c]

Let the request arrival rate follows Poisson Distribution, i.e., $\lambda$ is mean of Poisson Distribution.

Let the service time follows Exponential Distribution, i.e., $\mu$ is the mean of Exponential Distribution.

LetsLet's say, I have a grid of $c \times T$. Here $c=5$, i.e., in the Queueing process, there are 5 servers and 5 requests can be served at most concurrently. Let, $T=100$ is the number of time-slots that I need to simulate. Therefore, each block in the x-axis represents a time-slot and each block in the y-axis is the amount of resource required to serve a request.

For example,

Let the number of requests at the first time-slot is 3. The first and the third requests need service time of 2 times slots, while the second request requires service time of only 1 time-slot.

As a result, in the grid,

The first row will have two grid-element (first and second column) filled

The second row will have one grid-element (first column) filled

The third row will have two grid-element (first and second column) filled

Now, letslet's say, at the second time-slot, the number of requests is 5. In this case, due to the nature of Earling-B or m/m/c/c Queueing Process, only 3 more requests can be served at this particular time-slot as we already have two requests being served (first and third request arrived at first time-slot). Other requests are blocked or lost.

How do I generate the number of resources being used by the system in different time-slots?

Lets assume, $\lambda=0.2$ per time-slot

$\mu=2$ time-slots

How to generate number of points in a Queueing process?

I am considering the Earling-B or m/m/c/c Queueing Process as

QueueingProcess[\[Lambda], \[Mu], c, c]

Let the request arrival rate follows Poisson Distribution, i.e., $\lambda$ is mean of Poisson Distribution.

Let the service time follows Exponential Distribution, i.e., $\mu$ is the mean of Exponential Distribution.

Lets say, I have a grid of $c \times T$. Here $c=5$, i.e., in the Queueing process, there are 5 servers and 5 requests can be served at most concurrently. Let, $T=100$ is the number of time-slots that I need to simulate. Therefore, each block in the x-axis represents a time-slot and each block in y-axis is the amount of resource required to serve a request.

For example,

Let the number of requests at the first time-slot is 3. The first and the third requests need service time of 2 times slots, while the second request requires service time of only 1 time-slot.

As a result, in the grid,

The first row will have two grid-element (first and second column) filled

The second row will have one grid-element (first column) filled

The third row will have two grid-element (first and second column) filled

Now, lets say, at the second time-slot, the number of requests is 5. In this case, due to the nature of Earling-B or m/m/c/c Queueing Process, only 3 more requests can be served at this particular time-slot as we already have two requests being served (first and third request arrived at first time-slot). Other requests are blocked or lost.

How do I generate the number of resources being used by the system in different time-slots?

Lets assume, $\lambda=0.2$ per time-slot

$\mu=2$ time-slots

How to generate number of points in a m/m/c/c process with Poisson arrival and exponential service time?

I am considering the Earling-B or m/m/c/c process.

Let the request arrival rate follows Poisson Distribution, i.e., $\lambda$ is mean of Poisson Distribution.

Let the service time follows Exponential Distribution, i.e., $\mu$ is the mean of Exponential Distribution.

Let's say, I have a grid of $c \times T$. Here $c=5$, i.e., in the Queueing process, there are 5 servers and 5 requests can be served at most concurrently. Let, $T=100$ is the number of time-slots that I need to simulate. Therefore, each block in the x-axis represents a time-slot and each block in the y-axis is the amount of resource required to serve a request.

For example,

Let the number of requests at the first time-slot is 3. The first and the third requests need service time of 2 times slots, while the second request requires service time of only 1 time-slot.

As a result, in the grid,

The first row will have two grid-element (first and second column) filled

The second row will have one grid-element (first column) filled

The third row will have two grid-element (first and second column) filled

Now, let's say, at the second time-slot, the number of requests is 5. In this case, due to the nature of Earling-B or m/m/c/c Queueing Process, only 3 more requests can be served at this particular time-slot as we already have two requests being served (first and third request arrived at first time-slot). Other requests are blocked or lost.

How do I generate the number of resources being used by the system in different time-slots?

Lets assume, $\lambda=0.2$ per time-slot

$\mu=2$ time-slots

Source Link
Loading